Hilfe Warenkorb Konto Anmelden
 
 
   Schnellsuche   
     zur Expertensuche                      
The NEC 3 Engineering and Construction Contract - A Commentary
  Großes Bild
 
The NEC 3 Engineering and Construction Contract - A Commentary
von: Brian Eggleston
Wiley-Blackwell, 2008
ISBN: 9781405172820
392 Seiten, Download: 2375 KB
 
Format:  PDF
geeignet für: Apple iPad, Android Tablet PC's Online-Lesen PC, MAC, Laptop

Typ: A (einfacher Zugriff)

 

 
eBook anfordern
Inhaltsverzeichnis

  Contents 7  
  Preface 13  
  Author’s note 15  
  1 Introduction 17  
     1.1 Development of NEC contracts 17  
     1.2 Characteristics of NEC contracts 18  
     1.3 Structure of the NEC 3 Engineering and Construction Contract 20  
     1.4 Feedback from ECC 2 21  
     1.5 Changes from ECC 2 22  
     1.6 Points of interest in NEC 3 23  
  2 Main options 27  
     2.1 Introduction 27  
     2.2 Contract strategy 28  
     2.3 Option A – priced contract with activity schedule 34  
     2.4 Option B – priced contract with bill of quantities 37  
     2.5 Target contracts generally 38  
     2.6 Options C and D – target contracts 41  
     2.7 Option E – cost reimbursable contract 42  
     2.8 Option F – management contract 43  
     2.9 Option W1 – dispute resolution 43  
     2.10 Option W2 – dispute resolution 44  
  3 Secondary option clauses 46  
     3.1 Introduction 46  
     3.2 Option X1 – price adjustment for in.ation 48  
     3.3 Option X2 – changes in the law 48  
     3.4 Option X3 – multiple currencies 49  
     3.5 Option X4 – parent company guarantee 50  
     3.6 Option X5 – sectional completion 51  
     3.7 Option X6 – bonus for early completion 52  
     3.8 Option X7 – delay damages 53  
     3.9 Option X12 – partnering 58  
     3.10 Option X13 – performance bond 60  
     3.11 Option X14 – advanced payment to the contractor 61  
     3.12 Option X15 – limitation of contractor’s liability for design 63  
     3.13 Option X16 – retention 64  
     3.14 Option X17 – low performance damages 66  
     3.15 Option X18 – limitation of liability 67  
     3.16 Option X20 – key performance indicators 70  
     3.17 Option Y(UK)2 – Housing Grants, Construction and Regeneration Act 1996 71  
     3.18 Option Y(UK)3 – Contracts (Rights of Third Parties) Act 1999 72  
     3.19 Option Z1 – additional conditions 72  
  4 Contract documents 74  
     4.1 Introduction 74  
     4.2 Entire agreements 75  
     4.3 Clause 12.4 of NEC 3 76  
     4.4 Construction of contracts generally 76  
     4.5 NEC 3 documentation 77  
     4.6 Essential contract documents 78  
     4.7 Identified and defined terms 80  
     4.8 The contract date 80  
     4.9 Works information 82  
     4.10 Site information 85  
     4.11 Contract data 87  
     4.12 Schedules of cost components 87  
     4.13 Ambiguities and inconsistencies in the contract documents 90  
     4.14 Schedule of clauses referring to the works information 91  
  5 Key players 95  
     5.1 Introduction 95  
     5.2 Others 97  
     5.3 Actions 98  
     5.4 The employer 101  
     5.5 Express obligations of the employer 102  
     5.6 The project manager 103  
     5.7 Express duties of the project manager 106  
     5.8 The supervisor 110  
     5.9 Express duties of the supervisor 111  
     5.10 Communications 111  
     5.11 The project manager and the supervisor 116  
  6 General core clauses 118  
     6.1 Introduction 118  
     6.2 Actions 119  
     6.3 Identified and defined terms 119  
     6.4 Interpretation and the law 129  
     6.5 Communications etc. 131  
     6.6 Instructions 131  
     6.7 Adding to the working areas 131  
     6.8 Early warning 132  
     6.9 Ambiguities and inconsistencies 135  
     6.10 Illegal and impossible requirements 136  
     6.11 Prevention 137  
  7 Obligations and responsibilities of the contractor 142  
     7.1 Introduction 142  
     7.2 Design obligations, responsibilities and liabilities 145  
     7.3 Providing the works 147  
     7.4 The contractor’s design 149  
     7.5 Using the contractor’s design 152  
     7.6 Design of equipment 152  
     7.7 People 153  
     7.8 Working with the employer and others 154  
     7.9 Subcontracting 156  
     7.10 Other responsibilities 159  
     7.11 Express obligations of the contractor 161  
     7.12 Express prohibitions on the contractor 165  
  8 Time (and related matters) 167  
     8.1 Introduction 167  
     8.2 Starting and completion 170  
     8.3 Programmes 172  
     8.4 Revision of programmes 175  
     8.5 Shortened programmes 177  
     8.6 Access to and use of the site 178  
     8.7 Instructions to stop or not to start work 179  
     8.8 Take-over 181  
     8.9 Acceleration 183  
  9 Testing and defects 186  
     9.1 Introduction 186  
     9.2 Definitions and certificates 189  
     9.3 Tests and inspections 193  
     9.4 Testing and inspection before delivery 195  
     9.5 Searching and notifying defects 196  
     9.6 Correcting defects 198  
     9.7 Accepting defects 200  
     9.8 Uncorrected defects 201  
  10 Payments 204  
     10.1 Introduction 204  
     10.2 Assessing the amount due 207  
     10.3 Payments 210  
     10.4 Defined cost 213  
     10.5 Payments – main option A 213  
     10.6 Payments – main option B 217  
     10.7 Payments – main option C 218  
     10.8 Payments – main option D 223  
     10.9 Payments – main option E 223  
     10.10 Payments – main option F 224  
  11 NEC 3 compensation event schemes 226  
     11.1 Introduction 226  
     11.2 Changes in NEC 3 (from ECC 2) 228  
     11.3 Outline of procedures 232  
     11.4 Defining a compensation event 233  
     11.5 Compensation events as exclusive remedies 233  
     11.6 Fairness of the compensation event procedures 234  
     11.7 Unusual features of the compensation event procedures 235  
  12 Listed compensation events 236  
     12.1 Introduction 236  
     12.2 Omissions from the listed events 237  
     12.3 Works information related events 237  
     12.4 Employer’s default events 240  
     12.5 Employer’s risk events 242  
     12.6 Project manager/supervisor related events 243  
     12.7 Physical conditions 247  
     12.8 Adverse weather 250  
     12.9 Prevention 251  
     12.10 Measurement related events 252  
     12.11 Secondary option clause events 238 254  
  13 Notifying compensation events 257  
     13.1 Introduction 257  
     13.2 Notifications by the project manager 258  
     13.3 Notifications by the contractor 260  
     13.4 Project manager’s response to notifications 264  
     13.5 Last date for notification of compensation events 267  
  14 Quotations for compensation events 269  
     14.1 Introduction 269  
     14.2 Instructions to submit quotations 272  
     14.3 Instructions for alternative quotations 275  
     14.4 Submission of quotations 276  
     14.5 Status of the contractor’s quotations 278  
  15 Assessment of compensation events 281  
     15.1 Introduction 281  
     15.2 Changes from ECC 2 282  
     15.3 General assessment rules 283  
     15.4 Particular assessment rules 290  
     15.5 The project manager’s assessments 294  
     15.6 Implementing compensation events 296  
     15.7 Other .nancial remedies 297  
  16 Title 299  
     16.1 Introduction 299  
     16.2 Employer’s title to equipment, plant and materials 300  
     16.3 Marking equipment, plant and materials 301  
     16.4 Removing equipment 301  
     16.5 Objects and materials within the site 302  
  17 Risks and insurances 304  
     17.1 Introduction 304  
     17.2 Employer’s risks 308  
     17.3 Contractor’s risks 311  
     17.4 Repairs 311  
     17.5 Indemnity 312  
     17.6 Insurance cover 312  
     17.7 Insurance policies 313  
     17.8 Contractor’s failure to insure 314  
     17.9 Insurance by the employer 314  
  18 Termination 316  
     18.1 Introduction 316  
     18.2 Summary of NEC 3 termination provisions 320  
     18.3 Termination for ‘any reason’ 321  
     18.4 Termination under section 9 322  
     18.5 Reasons for termination 324  
     18.6 Procedures on termination 328  
     18.7 Amounts due on termination 329  
  19 Dispute resolution 331  
     19.1 Introduction 331  
     19.2 Developments in dispute resolution 332  
     19.3 Meaning of dispute 333  
     19.4 Adjudication under Option W1 335  
     19.5 Adjudication under Option W2 345  
     19.6 Review by the tribunal 349  
     19.7 The Adjudicator’s Contract 352  
  20 NEC 3 Engineering and Construction Subcontract 353  
     20.1 Introduction 353  
     20.2 Core clauses – general 355  
     20.3 Core clauses – the subcontractor’s main responsibilities 356  
     20.4 Core clauses – time 356  
     20.5 Core clauses – testing and defects 357  
     20.6 Core clauses – payment 357  
     20.7 Core clauses – compensation events 358  
     20.8 Core clauses – title 359  
     20.9 Core clauses – risks and insurance 359  
     20.10 Core clauses – termination 359  
     20.11 Dispute resolution 360  
  21 NEC 3 family of contracts 361  
     21.1 The contracts 361  
     21.2 NEC 3 Short Contract and Short Subcontract 362  
     21.3 NEC 3 Term Service Contract 364  
     21.4 NEC 3 Framework Contract 368  
     21.5 NEC 3 Professional Services Contract 368  
     21.6 NEC 3 Adjudicator’s Contract 370  
     21.7 Concluding comment 370  
  Table of cases 371  
  Table of clause references 375  


nach oben


  Mehr zum Inhalt
Kapitelübersicht
Kurzinformation
Inhaltsverzeichnis
Leseprobe
Blick ins Buch
Fragen zu eBooks?

  Navigation
Belletristik / Romane
Computer
Geschichte
Kultur
Medizin / Gesundheit
Philosophie / Religion
Politik
Psychologie / Pädagogik
Ratgeber
Recht
Reise / Hobbys
Sexualität / Erotik
Technik / Wissen
Wirtschaft

  Info
Hier gelangen Sie wieder zum Online-Auftritt Ihrer Bibliothek
© 2008-2024 ciando GmbH | Impressum | Kontakt | F.A.Q. | Datenschutz