|
Contents |
7 |
|
|
Preface |
13 |
|
|
Author’s note |
15 |
|
|
1 Introduction |
17 |
|
|
1.1 Development of NEC contracts |
17 |
|
|
1.2 Characteristics of NEC contracts |
18 |
|
|
1.3 Structure of the NEC 3 Engineering and Construction Contract |
20 |
|
|
1.4 Feedback from ECC 2 |
21 |
|
|
1.5 Changes from ECC 2 |
22 |
|
|
1.6 Points of interest in NEC 3 |
23 |
|
|
2 Main options |
27 |
|
|
2.1 Introduction |
27 |
|
|
2.2 Contract strategy |
28 |
|
|
2.3 Option A – priced contract with activity schedule |
34 |
|
|
2.4 Option B – priced contract with bill of quantities |
37 |
|
|
2.5 Target contracts generally |
38 |
|
|
2.6 Options C and D – target contracts |
41 |
|
|
2.7 Option E – cost reimbursable contract |
42 |
|
|
2.8 Option F – management contract |
43 |
|
|
2.9 Option W1 – dispute resolution |
43 |
|
|
2.10 Option W2 – dispute resolution |
44 |
|
|
3 Secondary option clauses |
46 |
|
|
3.1 Introduction |
46 |
|
|
3.2 Option X1 – price adjustment for in.ation |
48 |
|
|
3.3 Option X2 – changes in the law |
48 |
|
|
3.4 Option X3 – multiple currencies |
49 |
|
|
3.5 Option X4 – parent company guarantee |
50 |
|
|
3.6 Option X5 – sectional completion |
51 |
|
|
3.7 Option X6 – bonus for early completion |
52 |
|
|
3.8 Option X7 – delay damages |
53 |
|
|
3.9 Option X12 – partnering |
58 |
|
|
3.10 Option X13 – performance bond |
60 |
|
|
3.11 Option X14 – advanced payment to the contractor |
61 |
|
|
3.12 Option X15 – limitation of contractor’s liability for design |
63 |
|
|
3.13 Option X16 – retention |
64 |
|
|
3.14 Option X17 – low performance damages |
66 |
|
|
3.15 Option X18 – limitation of liability |
67 |
|
|
3.16 Option X20 – key performance indicators |
70 |
|
|
3.17 Option Y(UK)2 – Housing Grants, Construction and Regeneration Act 1996 |
71 |
|
|
3.18 Option Y(UK)3 – Contracts (Rights of Third Parties) Act 1999 |
72 |
|
|
3.19 Option Z1 – additional conditions |
72 |
|
|
4 Contract documents |
74 |
|
|
4.1 Introduction |
74 |
|
|
4.2 Entire agreements |
75 |
|
|
4.3 Clause 12.4 of NEC 3 |
76 |
|
|
4.4 Construction of contracts generally |
76 |
|
|
4.5 NEC 3 documentation |
77 |
|
|
4.6 Essential contract documents |
78 |
|
|
4.7 Identified and defined terms |
80 |
|
|
4.8 The contract date |
80 |
|
|
4.9 Works information |
82 |
|
|
4.10 Site information |
85 |
|
|
4.11 Contract data |
87 |
|
|
4.12 Schedules of cost components |
87 |
|
|
4.13 Ambiguities and inconsistencies in the contract documents |
90 |
|
|
4.14 Schedule of clauses referring to the works information |
91 |
|
|
5 Key players |
95 |
|
|
5.1 Introduction |
95 |
|
|
5.2 Others |
97 |
|
|
5.3 Actions |
98 |
|
|
5.4 The employer |
101 |
|
|
5.5 Express obligations of the employer |
102 |
|
|
5.6 The project manager |
103 |
|
|
5.7 Express duties of the project manager |
106 |
|
|
5.8 The supervisor |
110 |
|
|
5.9 Express duties of the supervisor |
111 |
|
|
5.10 Communications |
111 |
|
|
5.11 The project manager and the supervisor |
116 |
|
|
6 General core clauses |
118 |
|
|
6.1 Introduction |
118 |
|
|
6.2 Actions |
119 |
|
|
6.3 Identified and defined terms |
119 |
|
|
6.4 Interpretation and the law |
129 |
|
|
6.5 Communications etc. |
131 |
|
|
6.6 Instructions |
131 |
|
|
6.7 Adding to the working areas |
131 |
|
|
6.8 Early warning |
132 |
|
|
6.9 Ambiguities and inconsistencies |
135 |
|
|
6.10 Illegal and impossible requirements |
136 |
|
|
6.11 Prevention |
137 |
|
|
7 Obligations and responsibilities of the contractor |
142 |
|
|
7.1 Introduction |
142 |
|
|
7.2 Design obligations, responsibilities and liabilities |
145 |
|
|
7.3 Providing the works |
147 |
|
|
7.4 The contractor’s design |
149 |
|
|
7.5 Using the contractor’s design |
152 |
|
|
7.6 Design of equipment |
152 |
|
|
7.7 People |
153 |
|
|
7.8 Working with the employer and others |
154 |
|
|
7.9 Subcontracting |
156 |
|
|
7.10 Other responsibilities |
159 |
|
|
7.11 Express obligations of the contractor |
161 |
|
|
7.12 Express prohibitions on the contractor |
165 |
|
|
8 Time (and related matters) |
167 |
|
|
8.1 Introduction |
167 |
|
|
8.2 Starting and completion |
170 |
|
|
8.3 Programmes |
172 |
|
|
8.4 Revision of programmes |
175 |
|
|
8.5 Shortened programmes |
177 |
|
|
8.6 Access to and use of the site |
178 |
|
|
8.7 Instructions to stop or not to start work |
179 |
|
|
8.8 Take-over |
181 |
|
|
8.9 Acceleration |
183 |
|
|
9 Testing and defects |
186 |
|
|
9.1 Introduction |
186 |
|
|
9.2 Definitions and certificates |
189 |
|
|
9.3 Tests and inspections |
193 |
|
|
9.4 Testing and inspection before delivery |
195 |
|
|
9.5 Searching and notifying defects |
196 |
|
|
9.6 Correcting defects |
198 |
|
|
9.7 Accepting defects |
200 |
|
|
9.8 Uncorrected defects |
201 |
|
|
10 Payments |
204 |
|
|
10.1 Introduction |
204 |
|
|
10.2 Assessing the amount due |
207 |
|
|
10.3 Payments |
210 |
|
|
10.4 Defined cost |
213 |
|
|
10.5 Payments – main option A |
213 |
|
|
10.6 Payments – main option B |
217 |
|
|
10.7 Payments – main option C |
218 |
|
|
10.8 Payments – main option D |
223 |
|
|
10.9 Payments – main option E |
223 |
|
|
10.10 Payments – main option F |
224 |
|
|
11 NEC 3 compensation event schemes |
226 |
|
|
11.1 Introduction |
226 |
|
|
11.2 Changes in NEC 3 (from ECC 2) |
228 |
|
|
11.3 Outline of procedures |
232 |
|
|
11.4 Defining a compensation event |
233 |
|
|
11.5 Compensation events as exclusive remedies |
233 |
|
|
11.6 Fairness of the compensation event procedures |
234 |
|
|
11.7 Unusual features of the compensation event procedures |
235 |
|
|
12 Listed compensation events |
236 |
|
|
12.1 Introduction |
236 |
|
|
12.2 Omissions from the listed events |
237 |
|
|
12.3 Works information related events |
237 |
|
|
12.4 Employer’s default events |
240 |
|
|
12.5 Employer’s risk events |
242 |
|
|
12.6 Project manager/supervisor related events |
243 |
|
|
12.7 Physical conditions |
247 |
|
|
12.8 Adverse weather |
250 |
|
|
12.9 Prevention |
251 |
|
|
12.10 Measurement related events |
252 |
|
|
12.11 Secondary option clause events 238 |
254 |
|
|
13 Notifying compensation events |
257 |
|
|
13.1 Introduction |
257 |
|
|
13.2 Notifications by the project manager |
258 |
|
|
13.3 Notifications by the contractor |
260 |
|
|
13.4 Project manager’s response to notifications |
264 |
|
|
13.5 Last date for notification of compensation events |
267 |
|
|
14 Quotations for compensation events |
269 |
|
|
14.1 Introduction |
269 |
|
|
14.2 Instructions to submit quotations |
272 |
|
|
14.3 Instructions for alternative quotations |
275 |
|
|
14.4 Submission of quotations |
276 |
|
|
14.5 Status of the contractor’s quotations |
278 |
|
|
15 Assessment of compensation events |
281 |
|
|
15.1 Introduction |
281 |
|
|
15.2 Changes from ECC 2 |
282 |
|
|
15.3 General assessment rules |
283 |
|
|
15.4 Particular assessment rules |
290 |
|
|
15.5 The project manager’s assessments |
294 |
|
|
15.6 Implementing compensation events |
296 |
|
|
15.7 Other .nancial remedies |
297 |
|
|
16 Title |
299 |
|
|
16.1 Introduction |
299 |
|
|
16.2 Employer’s title to equipment, plant and materials |
300 |
|
|
16.3 Marking equipment, plant and materials |
301 |
|
|
16.4 Removing equipment |
301 |
|
|
16.5 Objects and materials within the site |
302 |
|
|
17 Risks and insurances |
304 |
|
|
17.1 Introduction |
304 |
|
|
17.2 Employer’s risks |
308 |
|
|
17.3 Contractor’s risks |
311 |
|
|
17.4 Repairs |
311 |
|
|
17.5 Indemnity |
312 |
|
|
17.6 Insurance cover |
312 |
|
|
17.7 Insurance policies |
313 |
|
|
17.8 Contractor’s failure to insure |
314 |
|
|
17.9 Insurance by the employer |
314 |
|
|
18 Termination |
316 |
|
|
18.1 Introduction |
316 |
|
|
18.2 Summary of NEC 3 termination provisions |
320 |
|
|
18.3 Termination for ‘any reason’ |
321 |
|
|
18.4 Termination under section 9 |
322 |
|
|
18.5 Reasons for termination |
324 |
|
|
18.6 Procedures on termination |
328 |
|
|
18.7 Amounts due on termination |
329 |
|
|
19 Dispute resolution |
331 |
|
|
19.1 Introduction |
331 |
|
|
19.2 Developments in dispute resolution |
332 |
|
|
19.3 Meaning of dispute |
333 |
|
|
19.4 Adjudication under Option W1 |
335 |
|
|
19.5 Adjudication under Option W2 |
345 |
|
|
19.6 Review by the tribunal |
349 |
|
|
19.7 The Adjudicator’s Contract |
352 |
|
|
20 NEC 3 Engineering and Construction Subcontract |
353 |
|
|
20.1 Introduction |
353 |
|
|
20.2 Core clauses – general |
355 |
|
|
20.3 Core clauses – the subcontractor’s main responsibilities |
356 |
|
|
20.4 Core clauses – time |
356 |
|
|
20.5 Core clauses – testing and defects |
357 |
|
|
20.6 Core clauses – payment |
357 |
|
|
20.7 Core clauses – compensation events |
358 |
|
|
20.8 Core clauses – title |
359 |
|
|
20.9 Core clauses – risks and insurance |
359 |
|
|
20.10 Core clauses – termination |
359 |
|
|
20.11 Dispute resolution |
360 |
|
|
21 NEC 3 family of contracts |
361 |
|
|
21.1 The contracts |
361 |
|
|
21.2 NEC 3 Short Contract and Short Subcontract |
362 |
|
|
21.3 NEC 3 Term Service Contract |
364 |
|
|
21.4 NEC 3 Framework Contract |
368 |
|
|
21.5 NEC 3 Professional Services Contract |
368 |
|
|
21.6 NEC 3 Adjudicator’s Contract |
370 |
|
|
21.7 Concluding comment |
370 |
|
|
Table of cases |
371 |
|
|
Table of clause references |
375 |
|